What Size Generator Do I Need for a House?

Generator size is about the loads you choose to run and their starting demands—not square footage alone. Build a first-pass load list, then verify nameplates and system design before buying equipment.

The short answer

List what must operate during an outage, find each item’s actual running and starting requirements, and decide which high-draw loads can be managed or left out. The result is a design input—not yet a generator recommendation.

Generac separates loads into essentials, comfort items and high-draw equipment. That is more useful than beginning with bedrooms or square footage because two similar homes can have very different pumps, heating systems, appliances and charging needs.

Step 1: divide loads by priority

Priority Examples to consider Decision
Essential Refrigerator/freezer, heating controls, sump or well pump, selected lights, router Which must continue for safety and basic function?
Comfort Microwave, garage door, extra receptacles, small room AC Which are useful but can wait or be staggered?
High-draw Central AC, electric range, dryer, well pump, EV charger Which are required, and how will starting/simultaneous load be handled?

Do not copy this list into a final design. A medical need, a finished basement below grade or a property with a well can change priorities substantially.

Step 2: find running and starting watts

Running watts are the power a load uses while operating. Starting or surge watts describe the additional short-term demand some motors need when starting.

Use the appliance nameplate or manufacturer documentation where possible. Generic tables can miss efficiency, motor type and model-specific starting behavior. For 240V and hardwired equipment, do not open panels or disconnect equipment just to find a label; ask for a professional assessment.

For this page’s simple screening exercise:

Planning load = sum of selected running watts + the largest additional starting surge among selected motor loads.

The additional surge is starting watts minus that appliance’s running watts. Using only the largest additional surge assumes starts can be staggered; it is not a universal engineering rule.

Worked example with invented values

This arithmetic example uses invented values to show the method. It does not describe your appliances or recommend a 5kW generator.

Example load Running watts Starting watts Additional surge
Refrigerator 700 2,100 1,400
Sump pump 800 2,000 1,200
Heating fan/controls 600 1,800 1,200
Lights and router 320 320 0
Microwave 1,200 1,200 0
Selected running total 3,620 — —

The largest additional surge is 1,400W. The screening total is 3,620 + 1,400 = 5,020W. A real design must still evaluate voltage, motor behavior, load sequence, continuous ratings, manufacturer guidance and other selected loads.

Use the planning calculator

Edit the example rows below or replace them with nameplate values. The calculator deliberately shows all arithmetic and does not round the answer into a branded generator size.

If your equipment lists amps rather than watts, leave the row for professional review instead of guessing at power factor or motor characteristics. For standby systems, manufacturer sizing tools and a measured site survey are the next step.

Portable versus standby sizing

Portable generator specifications commonly emphasize running and starting watts. Standby equipment is selected as a permanently installed system with transfer equipment, fuel and possible load management. Do not transfer a portable-generator rule directly to a standby purchase.

The safe connection question is independent of size. ESFI identifies transfer switching as the safe way to supply a home electrical system and warns against backfeeding. A larger generator does not make an unsafe connection acceptable.

How load management changes the question

High-draw equipment does not always need to run at the same instant. Compatible load-management equipment can defer or cycle selected loads so the generator remains within its operating limits.

That may avoid unnecessary capacity, but it is not permission to undersize essential loads. The design must define which loads are managed, their priority and what happens during an outage.

Common sizing mistakes

  • Choosing by square footage without listing electrical loads.
  • Adding every nameplate maximum while ignoring how the system will be operated.
  • Ignoring starting demands for pumps, refrigeration and air conditioning.
  • Assuming an EV charger must run at its maximum setting during an outage.
  • Treating open breaker spaces as proof of available generator or service capacity.
  • Buying the generator before planning transfer equipment, fuel and placement.

Take the load list into installation planning

Once the list is complete, use the home generator installation guide to plan transfer switching, fuel, placement and outage testing. The installed generator cost guide explains why different published totals describe different scopes.

For Worcester or Sutton, collect the site and permit details with the project planner.

Interactive planning tool

Generator load-list calculator

Replace the invented example values with equipment nameplate data. Nothing is uploaded or saved.

Screening exercise
Selected loadRunning WStarting WAdded surge
1400 W
1200 W
1200 W
0 W
0 W
Starting W can equal Running W when there is no added surge.
Selected running total3,620 W
Largest additional surge1,400 W
Screening total5,020 W5.02 kW before design review

This is not a generator recommendation. It assumes starts can be staggered and does not evaluate voltage, power factor, motor characteristics, continuous ratings or load management. Confirm the design with equipment documentation and a qualified site assessment.

Common questions

Frequently asked questions

Is a 22kW generator enough for a whole house?

Sometimes, but the label whole house does not prove suitability for every house. Actual major loads, motor starting and load management determine whether a given unit supports the selected scope.

How do I calculate generator size?

List selected loads and their running watts, account for motor starting demands, and consider which loads can be managed or staggered. This page uses running total plus the largest additional starting surge as a simple screening exercise, not an equipment selection rule.

Should I add every appliance's maximum wattage?

Not without considering the backup scope and simultaneous operation. Essential-load selection and load management can avoid designing for an unrealistic all-at-once peak, but required loads must still start and run reliably.

Can I size a standby generator from an online calculator?

Use a calculator to prepare, not to make the final purchase. Nameplates, motor characteristics, measured loads, transfer equipment and manufacturer requirements need a site-specific review.